Larkfield Leisure Centre Capital Schemes 2019/20 - Mechanical, Electrical and Roofing Work

Meeting: 09/07/2019 - Council (Item 63)

63 Larkfield Leisure Centre Capital Schemes 2019/20 - Mechanical, Electrical and Roofing Work pdf icon PDF 54 KB

Item CB 19/41 referred from Cabinet minutes of 5 June 2019

Additional documents:

Minutes:

Item CB 19/41 referred from Cabinet minutes of 5 June 2019.

 

RESOLVED:  That the recommendations at Minute CB 19/41 be approved.


Meeting: 05/06/2019 - Cabinet (Item 41)

41 Larkfield Leisure Centre Capital Schemes 2019/20 - Mechanical, Electrical and Roofing Work pdf icon PDF 57 KB

Item referred from Finance, Innovation and Property Advisory Board meeting held earlier in the evening. Copy of reports attached.

Additional documents:

Minutes:

(Item FIP 19/15 referred from Finance, Innovation and Property Advisory Board minutes of 5 June 2019)

 

The Cabinet received the recommendations of the Finance, Innovation and Property Advisory Board at its meeting of 5 June 2019 regarding the merits and cost implications of undertaking a combined package of works to ventilation, boilers, leisure pool hall roof and space frame at Larkfield Leisure Centre.

 

RECOMMENDED:  That based on independent advice and detailed financial appraisal:

 

(1)             the proposed scheme outlined in the report to undertake a package of works to ventilation, boilers, leisure pool hall roof and space frame at Larkfield Leisure Centre be approved;

 

(2)             the increased cost of £867,000 be met from the Leisure Trust reserve and the Revenue Reserve for Capital Schemes and the relevant revenue and capital budgets be amended accordingly;

 

(3)             the works be progressed to commence early October 2019 for a period of 36 weeks;

 

(4)             liaison continue with the Tonbridge and Malling Leisure Trust to minimise the impact of the works on customers and the loss of income claim to the Council; and

 

(5)             officers be requested to undertake a risk assessment with respect to Kier and report back to the next meeting of the Advisory Board on 17 July 2019.

*Referred to Council