Town Lock Capital Project

Meeting: 11/03/2014 - Planning and Transportation Advisory Board (Item 11)

11 Town Lock Capital Project pdf icon PDF 37 KB

Decision:

The report provided an update on progress and set out a programme for the implementation of the scheme.

 

Following consideration by the Planning and Transportation Advisory Board, the Cabinet Member for Planning and Transportation resolved that:

The progress made towards implementing the Town Lock capital project be noted and the programme as set out in the report be approved.

Minutes:

Decision Notice D140031MEM

 

The report provided an update on progress and set out a programme for the implementation of the scheme.

 

Members noted that a start date on site was now anticipated for July 2014, which allowed the majority of the work to be completed during the summer months when working conditions were most favourable.  Completion of the project would be around October/November dependent upon the contractor’s approved construction programme.

 

In addition, the Advisory Board had every confidence that the objectives of officers were the same as local Members in getting the Town Lock area reinvigorated.

RECOMMENDED: That the progress made towards implementing the Town Lock capital project be noted and the programme as set out in the report be approved.