46 Infrastructure Funding Statement 2023-24 PDF 144 KB
The Infrastructure Funding Statement sets out infrastructure delivery and contributions collected by TMBC, allocations made within the monitoring period, projects delivered within the relevant period and new agreements entered into with an outline of the contributions agreed over the 2023/24 period.
Additional documents:
Decision:
(Report of Cabinet Member of Transformation and Infrastructure and Director of Planning, Housing and Environmental Health)
Members reviewed the Infrastructure Funding Statement 2023/24 which set out the infrastructure delivery and contributions collected by the Borough Council, allocations made within the monitoring period, projects delivered within the relevant period and new agreements entered into. Contributions agreed over the 2023/24 period were also outlined.
The Borough Council had a statutory requirement under the Community Infrastructure Levey Regulations 2010 (Regulation 121A) to publish an annual Infrastructure Funding Statement (IFS) by the end of December each year. The purpose of the IFS was to provide a summary of all financial and non-financial developer contributions.
Following consideration by the Housing and Planning Scrutiny Select Committee, the Cabinet Member for Transformation and Infrastructure RESOLVED that:
(1) the Infrastructure Funding Statement and associated documents be endorsed; and
(2) the Infrastructure Funding Statement be approved for publication by the end of December 2024.
Minutes:
(Decision Number D240122MEM)
Members reviewed the Infrastructure Funding Statement 2023/24 which set out the infrastructure delivery and contributions collected by the Borough Council, allocations made within the monitoring period, projects delivered within the relevant period and new agreements entered into. Contributions agreed over the 2023/24 period were also outlined.
The Borough Council had a statutory requirement under the Community Infrastructure Levey Regulations 2010 (Regulation 121A) to publish an annual Infrastructure Funding Statement (IFS) by the end of December each year. The purpose of the IFS was to provide a summary of all financial and non-financial developer contributions.
Reference was made to the lack of a mechanism for Tonbridge to have an infrastructure statement and a different approach on how these funding requests could be put forward would be considered in discussion with Members and the Tonbridge Community Forum.
*RECOMMENDED: That:
(1) the Infrastructure Funding Statement and associated documents be endorsed; and
(2) the Infrastructure Funding Statement be approved for publication by the end of December 2024.
*Decision taken by Cabinet Member