Issue - meetings

Risk Management

Meeting: 10/02/2026 - Cabinet (Item 27)

27 Risk Management pdf icon PDF 87 KB

Consideration of recommendations of the Audit Committee in respect of the risk management process and the Strategic Risk Register. 

 

Recommendations are ‘to follow’ and will be circulated in advance of the meeting.

 

 

Additional documents:

Decision:

Consideration of recommendations of the Audit Committee in respect of the risk management process and the current status of the Strategic Risk Register (SRR).

 

Due regard was given to the views of the Committee, the financial and value for money considerations, the assessment of risk and the legal implications.

 

Cabinet noted that the risks categorised as ‘RED’ were:

 

·       Failure to adopt a Local Plan

·       Recruitment and retention of staff

·       Local Government Reorganisation in Kent

 

In recognition of the importance of efficient and effective risk management in protecting the Borough Council’s assets, employees and customers and ensuring value for money, Cllr Boughton proposed, Cllr Betts seconded and Cabinet

 

RESOLVED: That

 

(1)            the updates to the Strategic Risk Register since the last iteration with particular emphasis on those risks categorised as ‘RED’ (summarised above) and set out in Annexes 1 and 1(a) be noted; and

 

(2)            the service risks identified in Annex 2 be noted.

Minutes:

(Decision Notice D260016CAB)

 

Consideration of recommendations of the Audit Committee in respect of the risk management process and the current status of the Strategic Risk Register (SRR).

 

Due regard was given to the views of the Committee, the financial and value for money considerations, the assessment of risk and the legal implications.

 

Cabinet noted that the risks categorised as ‘RED’ were:

 

·       Failure to adopt a Local Plan

·       Recruitment and retention of staff

·       Local Government Reorganisation in Kent

 

In recognition of the importance of efficient and effective risk management in protecting the Borough Council’s assets, employees and customers and ensuring value for money, Cllr Boughton proposed, Cllr Betts seconded and Cabinet

 

RESOLVED: That

 

(1)            the updates to the Strategic Risk Register since the last iteration with particular emphasis on those risks categorised as ‘RED’ (summarised above) and set out in Annexes 1 and 1(a) be noted; and

 

(2)            the service risks identified in Annex 2 be noted.


Meeting: 26/01/2026 - Audit Committee (Item 5)

5 Risk Management pdf icon PDF 154 KB

The report of the Management Team provides an update on the risk management process and the Strategic Risk Register. 

Additional documents:

Minutes:

The report of Management Team provided an update on the risk management process and the current status of the Strategic Risk Register (SSR).  It highlighted the importance of efficient and effective risk management in protecting the Council’s assets, employees, and customers, as well as ensuring value for money and service continuity for residents.

 

The Risk Management Strategy, which outlined objectives and responsibilities, was endorsed by the Committee in September 2025 and adopted by Full Council in October 2025.  The Council had transitioned to a national 5x5 risk scoring matrix, categorising risks as AMBER (scores 8–12) and RED (scores 15–25), with procedures for escalating significant risks to the Corporate Management Team for inclusion in the Strategic Risk Register.

 

The Strategic Risk Register was regularly updated by the Management Team. An executive summary of RED (high) risks was provided, with a full version available in the annexes. Recent reviews had resulted in the removal of certain risks, such as Performance Management and Contract Procurement, due to improved protocols and external auditor feedback. However, some areas remained RED, including:

 

  • Failure to adopt a Local Plan
  • Recruitment and retention of staff
  • Local Government Reorganisation in Kent

 

Ongoing service risks and outcomes from the escalation process were reported to the Committee, and a schedule of current and newly identified risks was appended to the report at Annex 2.

 

During discussion regarding increasing demand on temporary accommodation, it was noted that instead of purchasing properties, the Council had opted to lease them, thereby limiting its direct exposure to property market risk and asset management challenges.  This strategy reflected an ongoing commitment to prudent risk management.  The Council was however exploring the potential to invest in council-owned temporary accommodation.  There was concern about the risk of over-supply, if demand did not materialise, which could lead to vacant properties and associated costs.  

 

RECOMMENDED*: That

 

(1)        the updates to the Strategic Risk Register since the last iteration, be noted, with particular emphasis on those risks categorised as RED as shown in Annexes 1 and 1(a); and

 

(2)        the service risks identified in Annex 2, be noted.

 

*Recommended to Cabinet